BrightWork 365 Templates

Video has been removed from this PDF. Visit the BrightWork 365 knowledge base to view.

All Templates

Also see our project template related best practice webinar.

Project Management Sections

Only templates that were created from a Content Template will be prepopulated with project data.

Charter

The Charter contains high level metadata about the project, including the project title and stakeholder information. Users granted the BrightWork Project Manager security role can be chosen in the Project Manager field. Users granted the BrightWork Team Member security role can be chosen in the Project Sponsor field.

Team

Automatically populates with the names of task assignees, and the earliest start dates and latest finish dates across all the work assigned to them.

Notes:

  • We do not support manually adding existing project team members from within the Team section. However, you can add a person to the Team without them being assigned to a work item by assigning them temporarily to a task, wait until they show up in the Team, and then unassign them from the task – they will stay in the Team.
  • To remove a Team Member, a user with a Project Manager or higher security role can remove the member from any assigned tasks, and then highlight the member's row in the grid and choose Delete Project Team Member in the section's top menu. 
  • Dates will not update in the Teams tab until an update of some kind is made in the Gantt, which will trigger the date update.

Gantt

List of project tasks with a corresponding bar chart that represents the project schedule with task start and end dates. Visually depicts dependency relationships between the tasks as well as task status. See also the Task Management article.

My Work

A list of all work of any type that is assigned to the logged in user.

Status

The Status screen displays current metrics and KPIs about the project and provides the project manager with the ability to create a snapshot status report of the project's current standing. See Status Reports.

Documents

Create new Microsoft Office documents and upload existing documents and store these files in the associated SharePoint document library.

Actions

Log project actions, decisions, and changes. See the Actions article for details.

Issues

In the Issues section you can create a new issue or add an existing issue from another project and assign to a team member. Project Issues can also be escalated to the project's associated program or portfolio by clicking into the Issue and choosing the relevant escalation location.

Risks

Enter Risk information for those items identified as potential future issues, with probability, impact, status and other relevant Risk details. Project Risks can also be escalated to the project's associated program or portfolio by clicking into the Risk and choosing the relevant escalation location.

Costs

Costs provides a comprehensive method for capturing and tracking project budgets and actual costs at the project and individual item levels. See the Costs article for details.

Communications

Initiate and save project related Emails and Appointments directly in the BrightWork 365 app and save these items as well as Phone Call details and Notes, within associated projects. See the Communications article for details.

Project Settings

The Project Settings screen provides additional project information and gives the project manager the ability to reset the baseline dates in all project tasks, and create a Microsoft Teams Channel for the Team associated with the project's related Program.

Only users with the BrightWork Project Manager or higher security role can view the Project Settings section.

Related

You can view documents related to entities within a project such as Issues or Risks, and project audit history by clicking on the Related tab.

Project Standard

Template Overview

The Project Standard template provides a semi-structured waterfall process that is useful for a range of business departments to run their projects including Sales, Marketing, Engineering, and Finance.


Project Management Sections

Only templates that were created from a Content Template will be prepopulated with project data.

Stages

  • Stages are automatically created via the Gantt section by setting the Task Type of a task to Stage in Task Details. We do not support manually adding stages from within the Stages section.
  • In the Stages section, the Current Stage detail values are tied to the progression of tasks within that Stage in the Gantt.

  • In the Stages section, the Current Stage column is controlled by the current stage in the Business Process Flow.
    Note: In order for this to work properly, the names of the stages in the Gantt must be named exactly the same as those in the Business Process Flow.
  • Click into a Stage link to view additional details about the Stage including Description and status information.


Business Process Flow

The Business Process Flow (BPF) in the Project Standard template has several predefined stages. In the BPF, the progression from one stage to the next stage is done manually by a user with the Project Manager or higher security role clicking on the current stage and then clicking Next Stage.


Default Project Standard Template Forms

New Product Introduction

Template Overview

The New Product Introduction template has a series of project management tabs, fields, and a Business Process Flow (BPF) that relates to the submission of a new product idea and managing the delivery of the new product. This template is on the higher end of the project management process maturity scale.


Project Management Sections

Only templates that were created from a Content Template will be prepopulated with project data.

Stages

  • Stages are automatically created via the Gantt section by setting the Task Type of a task to Stage in Task Details. We do not support manually adding stages from within the Stages section.
  • In the Stages section, the current stage detail field values are tied to the progression of tasks within that Stage in the Gantt.

  • In the Stages section, the Current Stage column is controlled by the current stage in the Business Process Flow.
    Note: In order for this to work properly, the names of the stages in the Gantt must be named exactly the same as those in the Business Process Flow.
  • Click into a Stage link to view additional details about the Stage including Description and status information.

Business Process Flow

The Business Process Flow (BPF) in the New Product Introduction template has several predefined stages. In the BPF, the progression from one stage to the next stage is done manually by a user with the Stage Mover security role clicking on the current stage and then clicking Next Stage.


Default New Product Introduction Template Forms

Product Update

Template Overview

The Product Update template is used to request projects for complex support issues. It follows a gated approach with approvals required to move from the Charter stage into Execution, and to close out the project.


Project Management Sections

Only templates that were created from a Content Template will be prepopulated with project data.

Charter

  • The Charter contains high level metadata about the project, including project title, stakeholder information, parent Program & Portfolio, and Location.
    • The Location drop-down menu choices that are found in the Product Update template are configured in Admin Area | Locations.

Stages

  • Stages are automatically created via the Gantt section by setting the Task Type of a task to Stage in Task Details. We do not support manually adding stages from within the Stages section.
  • In the Stages section, the current stage detail field values are tied to the progression of tasks within that Stage in the Gantt.

  • Click on a Stage link to view additional details about the stage including description and status information.

Project Settings

  • The Project Settings screen provides additional project information and gives the Project Manager the ability to reset the baseline dates in all project tasks, and to create a Microsoft Teams Channel for the Team associated with the project's related Program.
  • The Project Settings screen is also used for project stage approval purposes as detailed in the Business Process Flow section below.
  • Approvals History: A history of project stages and the related approval request outcomes can be viewed in the Approvals History window.


Business Process Flow

The Business Process Flow (BPF) in the Product Update template has several predefined stages. In the BPF, the progression from one stage to the next is tied to the status of the BPF Stage approval requests triggered in Project Settings.

  • When Send Charter and Gantt for Approval is set to Yes in Project Settings, an email is sent to the Project Manager, Project Sponsor, and Group Manager seeking approval. After all these users have submitted their approval, the BPF will automatically progress to Execution.
    • The BPF can be set back to Chartering from any other stage if a user with proper permissions clicks on the BPF Chartering stage and then clicks the Set Active button.

      The relevant BPF Stage approval request switches in the Project Settings tab will once again be set to No.
       
  • When Move to Close Out is set to Yes in Project Settings, the BPF will automatically progress to Close Out. Refresh the page to enable the setting Send Close Out for Approval that will be used at a later time.
  • When you're ready to fully close the project, in Project Settings set Send Close Out for Approval to Yes, and after the Project Manager, Project Sponsor, and Group Manager all submit their approvals, the BPF will automatically progress to Closed.

Default Product Update Template Forms